Site walkthrough — Tower B, 4th floor
Rakesh (PM) · Imran (contractor) · Sunita (architect)
Fourth floor ka waterproofing abhi tak pending hai.
04:18Material aa gaya hai, Monday se start kar denge.
04:35The window reveal on the east face does not match the drawing.
06:02Decisions
- Waterproofing on the 4th floor starts Monday.
- East-face window reveals to be re-checked against revision C of the drawing.
Action items
- Start 4th floor waterproofing Imran
- Share revision C drawings with the contractor Sunita